Adding fixed costs to tasks
1. On the Workflow bar, click the Cost Analysis view.
2. Select the task in which you want to fixed costs.
3. Enter base fixed cost in the Cost field. You can enter in Low and
High estimated costs.
4. Select an accrual method in the Accrual column. Accrual methods
indicate how cost is accrued in the task. Default accrual method if
defaulted in Tools -> Options, cost tab separately for cost. Accrual
methods available are:
• Start
• Finish
• Prorated
•
You may assign fixed cost to the summary tasks the same way as they
are assigned to the subtasks
• You may define uncertainties in fixed cost using low, base
and high values of cost.
• Uncertainty in variable cost is originated in task work
since variable cost = resource work * number of units * rate.
See also
Setting up your projects
|