Calculating and Reassessing tasks using tracking
data
RiskyProject uses tracking information for probabilistic
calculations. The purpose of the calculation is to reassess the task
duration, start, and finish dates based on the actual progress. As
the deterministic current project schedule remains unchanged, you
can compare your original estimates with the forecasted schedule.
Probabilistic tracking calculations are performed in the following
manner:
• If a task has tracking information, new forecasted task
duration and finish times are calculated. The results of this
calculation are instantly plotted on the tracking chart as a green
rectangle. The task’s start time is actual start time entered in the
tracking data.
• The actual start time, forecasted task duration, and finish
time are used for probabilistic calculations. If the percentage
complete is greater than 0%, the Low, Base, and High durations are
not used.
• If the task has risks assigned to it (global or local), the
chance of the risk is recalculated based on the current time, when
the risk occurred, and the task completion percentage.
• If the percentage completed equals zero, all risks are used
with their original chances of occurrence.
• If the percent completed equals 100, the chance of
occurrence for all risks is internally set to zero. Although the
original chance of risk occurrence is not changed, it is important
to note that the actual outcome of risks changes.
Example
Originally, a task had duration of 10 days and there was a 20%
chance that the task would be delayed 15% or 1.5 days. However,
because of tracking information, the duration was forecasted to be
20 days. In this case, the chance of the risk occurrence is
recalculated internally and reduced. However, the delay is
recalculated based on forecasted duration and now equals 3 days (20
days * 15%).
See also
Tracking Performance
Tracking Results
|