Calculations
RiskyProject has two types of calculations:
•
Deterministic calculation of current schedule - The
default calculation automatically performed when you modify a
project schedule. As this calculation occurs automatically, you do
not need to press the Calculation button. This calculation uses the
Base input parameters (duration, start time, lag) without
calculating the effect of risk or uncertainty.
• Probabilistic (Monte Carlo simulations) – Use
this to calculate the project schedule and costs with uncertainties
and risks.
Running probabilistic calculations
• Click the Calculation button on the
Standard toolbar. You may cancel the probabilistic
calculation at any time; however, if number of simulations performed
is less than 20, no probabilistic results will be calculated.
See also
RiskyProject Calculation Options
Defining the number of simulations
|