How correlated risks are calculated


 Risk correlations can only be defined in the Global Risk Assignment or Local Risk Assignment views.
1. Right-click on the risk and choose Risk and Mitigation from the shortcut menu.
2. Click the Correlations tab.
3. Select a risk from the list of all available risks.
4. Select the task or resource to which this risk is assigned. This is required when risks with the same name are assigned to different resources or tasks.
5. Click OK to save this information.

 

See also

Risk Correlations

Assigning local and global risks