Enabling and disabling risks
You
can enable or disable each risk assignment. If risk assignment is
disabled it does not affect project schedule and calculation to risk
impacts. However, it stays in the risk register and remains assigned
to the tasks or resources.
1. Open a risk assignment view:
• Global Risk Assignment view
• Local risk assignment views for tasks and resources
• Risk tabs in the Task Information and Resource
Information dialog boxes.
2. Enable a risk by clicking on the check box beside the
Risk name. Clear the check box to disable the risk.
See also
Risk Register
Assigning local and global risks
|