RiskyProject Reports
RiskyProject Professional offers the following set of customizable
reports
1. Project dashboard:
view three most important project parameters (project duration,
start and finish times with and without risks), three crucial tasks,
and three critical risks
2. Current
Schedule Report view: use the Current Schedule Report to view
original low, base, and high task durations, start, and finish
times. Gantt chart will not be shown.
3. Results Report view is similar to Current Schedule Report View, but
shows the results of the probabilistic analysis. You can use these
views for the reporting and analysis of your results.
4. Revenue Report
view shows input data and results associated with cost, income, and
revenue.
5. Task
Report: detailed information about all tasks (new in RiskyProject
Professionals 3.2)
6. Risk
Report: detailed information about all risks (new in RiskyProject
Professional 3.2)
RiskyProject
Lite includes only one reporting view:
- Project
dashboard: view three most important project parameters (project
duration, start and finish times with and without risks), three
crucial tasks, and three critical risks
Setting up reports for printing
See Report Setup Dialog to
setup reports for printing
Printing reports
• From the File menu, choose Print.
Previewing reports
• From the File menu, choose Print Preview.
Copying data to the Clipboard
You can copy project data to the clipboard, so that you can use it
in another applications. You can also copy data, associated with
charts to the clipboard: These charts are:
• Gantt charts, including simulation Results chart,
• Probability Density charts, and
• Tracking chart
• Tracking chart within Tracking Tab of the Task information
dialog box
|