Risks and Issues
RiskyProject manages both risks and issues. Risks are an event that
may occur. Issues are an event that has already occurred. When you
enter new record to the risk register, it is a risk.
You may switch between risks or issues. When you switch risk to
issue, chance of occurrence of the issue would be 100%.
Converting a risk to an issue
1. On the Risks tab of the Workflow
bar, click the Risk Register view.
2. Double-click on risk ID. Risk information dialog will come up.
3. On a Properties tab, select Issue.
•
If you switch from issue to risk, probabilities for all risk
assignments will remain 100%. You would have manually assign
probabilities to actual number of all risk assigned after switch it
from issue to risk.
• If the risk has mutually exclusive alternatives as part of
risk assignment and this risk is switched to the issue, chance of
occurrence will not change. In this case, it is recommended manually
remove mutually exclusive alternatives, keep only one alternative
and set it chance of occurrence to 100%.
See also
Risk register and issue management
Risk Register
Risks in RiskyProject
|