Task calendars
Task calendars make it possible to schedule tasks during nonworking
time, as defined by the project calendar or resource calendar. For
example, you can set up a task calendar if you have a task that
needs to be worked on overnight or through the weekend.
You create a task calendar in the Working Time dialog box as a new
base calendar. You then apply the base calendar to a task by using
the Advanced tab in the Task Information dialog box.
If you have applied a task calendar to a task that already has
assigned resources, by default, the task is scheduled for the
working times of resource calendars. If you want to schedule the
task by using only the task calendar, select the Ignore Resource
Calendars check box on the Advanced tab in the Task Information
dialog box.
See also
Base calendars
CreateBaseCalendar
Creating a new calendar
Defining working time
|