Name of parameters (shown on the tool tip) |
Start time
of the
risk occurrence |
|
|
Type of the field |
Edit Box with Spin
Control |
|
|
Short name (shown in the
header) |
Start
|
|
|
Description |
Risk can
only occur after
this
time.
Time is defined as a percent of total
task duration. For example, task duration is 5
days. Start time of risk
occurrence 20% means that risk will occur starting second day.
|
|
|
Related
Fields |
Moment of Risk Distribution chart
Finish time of the risk occurrence Most likely time of the risk
occurrence
|
|