Description |
Base Task Duration is used to calculate the baseline schedule. It also used to calculate the duration of each iteration of the probabilistic calculation. For these calculations, base duration is used differently depending of statistical distribution. For example, for uniform distribution Base Task Duration is ignored. See “How to define distribution for Start Time, Cost, and Duration” for details. |
|