User's Guide to  

RiskyProject

Back to RiskyProject
Project Risk Management and Decision Analysis 

Site search powered by Google

Task Related Fields

Duration High- Current Schedule

Name of parameters (shown on the tool tip)

Duration High- baseline

Type of the field

Edit Box with Spin Control

Short name (shown in the header)

High Dur

Description

igh Task Duration is used to calculate the duration of each iteration for probabilistic analysis. The particular meaning of high duration depends on statistical distribution. For example for normal and lognormal distributions, it can be P90, P95, or P99. High duration does not affect current schedule.

Related Fields

Duration Base- baseline

Duration Low - baseline


www.intaver.com products      solutions      support      partners      technology      company

Copyright © Intaver Institute Inc., 2002-2006. All Rights Reserved