Description |
Editable text, which
represent list of predecessors for the current task. Example:
1+3day, 1SF+4day. It means: that predecessors are task 1
Finish-Start relationship with lag 3days and task 2
(Start-Finish relationship) with lag
4 days. Start-Finish is displayed as SF, Start-Start is SS, Finish-Finish is
FF. Finish-Start does
|