Name of parameter (shown on the tool tip)

Predecessors

Type of the field

Static text

Short name (shown in the header)

Predecessors

Description

Editable text, which represent list of predecessors for the current task. Example: 1+3day, 1SF+4day. It means: that predecessors are task 1 Finish-Start relationship with lag 3days and task 2 (Start-Finish relationship) with lag 4 days. Start-Finish is displayed as SF, Start-Start is SS, Finish-Finish is FF. Finish-Start does

 