Revenue High result

Name of parameters (shown on the tool tip)

Revenue High  - result (P90, P95, P99, or max)

Type of the field

Static text

Short name (shown in the header)

Revenue

Description

Revenue = Income – Cost on each iteration. If Income is zero for all tasks, revenue is not calculated. High Revenue is calculated as result of statistical analysis. Will have no value in the current schedule calculation. Can be maximum, P90, P95, P99. It is defined in Options (Calculation tab).

Related Fields

Revenue Base
Revenue Mean- result
Revenue Low - result

 