Name of parameters (shown on the tool tip) |
Revenue High - result
(P90, P95, P99, or max) |
|
|
Description |
Revenue = Income – Cost on each iteration. If Income
is zero
for all tasks, revenue is not calculated. High Revenue is
calculated as result of statistical analysis. Will
have no value in the current
schedule calculation. Can be maximum, P90, P95, P99. It is
defined in Options (Calculation
tab).
|
|