Task Related Fields
Start Time of the task
(Low)
|
Name of parameters (shown on the tool tip) |
Start Time
of
the task (Low)
|
|
|
Type of the field |
Date Control |
|
|
Short name (shown in the
header) |
Start
Low
|
|
|
Description |
Low Start Time
is used for probabilistic calculations and does not
affect the current project schedule. If you modify the Low Start Time,
the Constraint is set to Must Start On”. See “Start,
Finish Times, and Constraints” for more details. Particular
meaning of low start time depends on the statistical
distribution for start time. See “How to
define distribution
for Start Time, Cost, Income and Duration” for details.
|
|
|
Related
Fields |
Start Time of the task
(High) Start Time of the task (Low)
|
|
|