Glossary
Constraint
A restriction that is set on the start or finish
date of a task. If you enter a new task by specifying parameters
(task name, duration, etc.) rather than start and finish dates,
RiskyProject does set constraint and task will start and finish as
soon as possible. If you specify a start date, a constraint is set
to Start No Later
Than. If you specify a finish date, a
constraint is set to Must
Finish On. You can change or remove constraints
in the General tab of the Task Information dialog box. Constraints
for start or finish dates are
indicated using an orange background in all
views.
|