Success Rate
The chance that a task or project will be completed. A task success
rate of 56% means that there is a 56% chance that this task will be
completed and 44% percent chance that task will be canceled. Tasks
can be canceled when either it reaches a task or project deadline,
or if a risk with a Cancel task, Cancel Task + all successors or
Cancel Project outcome type occurs. Projects can be canceled either
when it reaches the project deadline or if a task risk with a Cancel
Project outcome occurs. The task success rate is presented on the
Success Rate view, but it can be requested within any view. The
Project success rate is shown in the Project Information view.
|