Glossary
Task Dependencies
The type of link between different tasks. There are four types of
task dependencies:
• Finish-To-Start: Task 2 (successor) cannot start until task
1 (predecessor) finishes
• Start-To-Start: Task 2 (successor) cannot start until task 1
(predecessor) starts
• Finish-To-Finish: Task 2 (successor) cannot finish until
task 1 (predecessor) finishes
• Start-To-Finish: Task 2 (successor) cannot finish until task
1 (predecessor) starts
Task dependencies can be defined in Task Information dialog box
(predecessor tab). They also can be defined toolbar button within
standard toolbar.
|