Variable and Fixed Costs
There are two types of costs in RiskyProject:
• Fixed costs, which are associated with tasks; and,
• Variable costs, which are associated with resources.
Costs associated with resources are calculated based on rate, units
assigned, and work of the particular resource.
Fixed cost can be accrued at the beginning of the task, at end of
the task or be prorated.
See
also
Analyzing Cost
|