Importing data from other project management software and keeping risk assignment
Sometimes you may want to import a project schedule from Microsoft Project or other software and keep existing risk assignment. It can be useful when you imported project schedule from Microsoft Project or other software, assigned risks in RiskyProject, and then updated project schedule in Microsoft Project.
1. On the File menu, click Import.
2. Select the format type of your project data ( XML, MPP, or MPX).
3. Select whether or not you want to import the risks already assigned to the project. RiskyProject will associate assigned risks with new tasks based on unique task IDs. However if you rename a task in Microsoft Project, this will remove all risk links to the renamed task.
Due to
the specific features of each application and the probabilistic
nature of RiskyProject data, in very rare cases there can
discrepancies in the original project schedule and imported schedule
in RiskyProject.
See
also
Importing
Project Schedules
Exporting
Projects
|