Importing data from other project management
software and keeping risk assignment
Sometimes you may want to import project schedule from Microsoft
Project or other software and keep existing risk assignment. It can
be useful when you imported project schedule from Microsoft Project
or other software, assigned risks in RiskyProject, and then updated
project schedule in Microsoft Project.
1. On the File menu, click Import.
2. Select the format type of your project data ( XML, MPP, or
MPX).
3. Select whether or not you want to import the risks already
assigned to the project. RiskyProject will associate assigned risks
with new tasks based on unique task IDs. However if you rename a
task in Microsoft Project, this will remove all risk links to the
renamed task.
See
also
Importing Project Schedules
Importing Project Schedules
|