Resource calendars
Resource calendars make sure that work resources (people and
equipment) are scheduled only when they are available for work. They
affect a specific resource or category of resources. By default, the
working time settings in the resource calendar match the project
calendar. However, you can customize the resource calendar to show
individual schedule information, such as vacations, leaves of
absence, or equipment maintenance time.
When you create a resource, the default resource calendar will be
created. You may view this resource calendar in Working Time dialog
box. By choosing Working Time from the Tools menu, you can edit
resource calendars to indicate nonworking time. You can also create
or assign different base calendars for individual resources to
indicate specific working hours. For example, you can assign a
resource to a calendar that you created for carpenters who may be
working during a time that is different from other workers. You can
edit Base calendars for each resource in the Working Time dialog
box.
When RiskyProject schedules the project, it uses the resource
calendar to schedule the tasks that that have resources assigned.
For example, if a resource has a week of vacation specified on his
or her resource calendar, RiskyProject will not schedule the task
for that week.
If you have resources that work alternative schedules, such as
part-time or the night shift, we recommend that you set up and apply
a separate base calendar for each shift. Use resource calendars to
accommodate exceptions to individual resource's working times.