Task
Information Dialog: General Tab
General Tab if task information is used to define:
- Task
start and finish times (low, base, and high)
- Task
duration (low, base, and high)
- Task
constraints
Entering
duration is the best way to schedule the task. If you enter Start
Time, the constraint will be set to "Must Start On".
You you enter Finish Time the constrain will be set to "Must
Finish On". If constraint type is "Start not early
than" you would need to define a date, associated with the
constraint.
You may
also use this dialog to enter notes for the task.
See also
Project
Tasks
Constraints
|