Project Tasks
When you first start RiskyProject, the Gantt view opens. Start the
scheduling process by adding tasks. Each task should have a name and
a base duration. You may enter this information directly onto the
datasheet or using the Task Information dialog box.
Opening the Task Information dialog box
The Task information dialog box can be used to enter task parameters
(duration, start, finish times, assign resources to tasks, assign
risks, etc.). You can open the task information dialog can in
invoked using one of the following ways:
• Double click on Task ID
• Right click on task ID and Select Task Information
• Select Task and click on Project
> Task Information
Entering task name and duration
When you create a task, the first step is to enter a name and a base
duration.
1. Click on the Task Name field in
the Gantt view.
2. Provide a name for task.
3. Enter a base duration in the Base
Duration field.
The
default Start Time for tasks is defined in the Calendar tab of the
Options dialog box. The start time can be either the current date or
a project start date, defined in Project ->Main Project Settings.
You can always change start time using constraints (see Start,
Finish Times and Constraints). You can also change other default
parameters in the Options dialog box.
Define
task durations using the Base Duration column. Once you have added
all of the tasks, you can add uncertainties by assigning low and
high durations. See Define Distributions for Start Time, Cost, and
Duration for more information.
See
also
Project Tasks
Task Deadlines
Task Links
Task Deadlines
Task calendars
|