Comparing pre and post-mitigation baselines
1. Open the Risk Register view
(Risk tab of the workflow bar)
2. Click the Configure Pre
and Post Mitigation button.
3. Select baselines for Pre and Post
Mitigation.
See
also
Analyzing Risk Mitigation Efforts with Multiple Baselines
Converting a baseline to a current schedule
Creating a mitigation or risk response plans
Assigning a mitigation or risk response plan to a task
|