Converting a baseline to a current schedule

1. On the Tools menu, click Manage Baselines. The Manage Baselines dialog box opens.
2. Select a baseline you want to make current using a check box on the left from baseline name.
3. Click OK.

See also

Analyzing Risk Mitigation Efforts with Multiple Baselines

Comparing pre and post-mitigation baselines

Creating a mitigation or risk response plans