Creating a baseline
Once you have run a simulation on your project, you can save the
results as a baseline.
1. On the Tools menu, choose Create
or Update Baseline.
2. Enter a name for the baseline. By default, it is assigned
“Baseline #_”
3. Select the type of results (Low, Base,
High, specific percentile, or
Deterministic) that you want to use for your
baseline.
4. Click OK.
5. If you are using probabilistic results for the baseline, you are
prompted to disable all risks and uncertainties from the schedule.
• Choosing Yes will in effect create a
deterministic baseline out of the results you selected.
• Choosing No will mean that all risks
and uncertainties will remain. If you calculate this baseline again,
this may cause a double count of the risks and
uncertainties.
See
also
Analyzing Risk Mitigation Efforts with Multiple Baselines
Comparing pre and post-mitigation baselines
Converting a baseline to a current schedule
Creating a mitigation or risk response plans
|