Use Customize report button of Task Report view to enable/disable
the following information:
General
task information (task duration, start and finish time, and
costs): see General
tab of Task information dialog or Cost
and Revenue view
Predecessors:
see Predecessor tab
of Task Information Dialog
Successors:
successors are explicitly presented in Branching
tab and Decision
tab of Task information dialog; successors are defined through
defining of predecessors in Predecessor
tab of Task Information Dialog
Advanced
task information: task calendars, task type (Fixed Units, Fixed
Duration, Fixed Work), Milestones, and other information (see Advanced
tab of task information dialog)
Task
notes: see General
tab of Task information dialog